Our new pavilion is coming to completion with almost all external works completed, aside from car park/and driveway access from Reserve Rd.
Power connection issues have caused some delays and the Council is working closely with VP, David Richards, to provide a timeline for handover for our winter season. Updates will follow as we close in on our winter tenancy of the ground itself starting on 1 April 2022, and hopefully our new club room soon afterward.
There is a multitude of tasks that the Club needs to complete in terms of our own fit out and usage of the new rooms, and a volunteer sub-committee has been formed to facilitate this exercise. If you are able to assist please contact Pete Allison on 0404 480533 /pallison@brandpack.net.au
Comentarios